Work on the freeway has been progressing eastward from Azle since the 2000s. This project will cross Lake Worth, and future work will take the freeway to IH 820.
High resolution
This view looking northwest shows the existing bridge on the left and work in progress for the piers in the lake.
(Photo date: 26-Sept-2021)
(Photo date: 26-Sept-2021)
(Photo date: 26-Sept-2021)
Looking northwest on the east side of the project.
(Photo date: 26-Sept-2021)
(Photo date: 26-Sept-2021)
Driver's view going eastbound on the west side of the lake.
(Photo date: 26-Sept-2021)
Looking east on the east side of the lake.
(Photo date: 26-Sept-2021)
High resolution
The following photos were taken on September 19, 2022. This view looks northwest along SH 199 on the east side of the Lake
(Photo date: 19-Sept-2022)
(Photo date: 19-Sept-2022)
High resolution
In September 2022 all piers were built, and beams were being placed between the piers.
(Photo date: 19-Sept-2022)
This view shows the east end of the bridge.
(Photo date: 19-Sept-2022)
Driver's view going westbound on SH 199.
(Photo date: 19-Sept-2022)
High resolution
Driver's view of the west end of the bridge.
(Photo date: 19-Sept-2022)